DOTY BROTHERS
SoCal Gas Company
PROJECT #3
Southern California Gas Company
This project is the relocation of approximately 1,500’ of 36” gas pipeline. The project was located on Benson Ave. overpass of the 60-freeway in Chino, CA. The existing pipeline was installed within the bridge casing and was planned to be installed by a horizontal directional bore (HDD) under the 60-freeway to limit the impact of the freeway. The project included coordinating with Caltrans, different cities and various property/commercial owners as the project progressed through the various stages (i.e., excavation, fabrication, boring under the freeway, installing the pipeline, backfilling, and final paving).
- Location: Chino, CA
- Timeline: January 2020 to July 2020
- Construction Methods: Horizontal Directional Bore
- Customer: Southern California Gas Company